Project Description:

This project consists of replacing  existing Cooling Towers ,  structural steel for new cooling towers, demolition of existing roof and install new, asbestos abatement, new piping, new pumps,  The new cooling towers runs on VFD’s therefore saving energy. The new fan of the tower was also designed in such a way so that it consumes minimum energy.  The new controls  system  saves and conserves energy as well.

A  SERVICE DISABLED VETERAN OWNED COMPANY

90 Dayton Ave, Bldg 16C, Ste 205 A/B, Passaic, NJ 07055 ♦ 973-685-7216 ♦ www.concentricgroup.biz

 

Replace Cooling Towers

VAMC Bronx Campus

@ Remove existing cooling tower

@ Structural steel

@ New piping

@ New pumps

@ New electrical & Controls

@ Install new cooling towers

@ Demolition of existing roof

@ Asbestos abatement

@ New Roofing

 

 

 

 

Scope of Work:  

Contract Amount: $4,593,471

Duration: Oct 11, 2011—Sep 15, 2013

Owner:

Department of Veterans Affairs

Network Acquisition & Logistics

130 Kingsbridge Road

Bronx, NY 10468

 

 

Owner Contact:

Patricia Cordero, Contracting Officer

718-584 9000 x 4928